Temporary power for Perth building sites: how the process works

WA Temporary Power (EC008678) installs temporary poles and meter connections for builders and owners across greater Perth and selected country regions. This page explains how to choose a connection and who does what. It does not quote Western Power or Synergy fees or timeframes. Those are published by them and they change. Last reviewed 9 November 2026.

Choose a connection

Use a long pole on an empty block with overhead supply and no meter. Use a dwarf pole where a Western Power dome is already on site. Use an end-of-run pole when your electrician has already run consumer or sub mains to the future meter position, which is common on battleaxe blocks. Use a pit connection when the supply comes from a ground-level Western Power pit. Use renovation power when an existing house meter has to move onto a temporary pole during a renovation. Single-phase and three-phase are both nominated on the application; tell us which supply the site needs.

What is the difference between a long pole and a dwarf pole in Perth?

A long pole is an overhead connection for an empty block. We open the temporary Synergy account in our name. A dwarf pole is an underground connection for a site that already has a Western Power dome. You hold the Synergy account, and power is live when we leave the second visit.

What is an end-of-run pole?

It is a pole at the end of consumer mains or sub mains that your electrician has already installed to the future meter-box position. It suits battleaxe and rear blocks, and sites where a normal trench is not possible. We then fit a permanent meter.

What is a Western Power pit connection?

It is an energised connection from a flat, ground-level Western Power pit. We are accredited to enter these pits. An additional pit-entry fee applies each time we enter, except when we are removing a temporary meter at disconnection.

Who applies for the Synergy account?

For a long pole, we open the temporary account in our name. For a dwarf pole, you apply online or by phone and write the Synergy reference number on our form. Synergy uses different reference types for temporary and permanent accounts. We tell you which application your site needs. This page does not restate Synergy’s account codes.

What does WA Temporary Power do, and what does Western Power do?

We install the pole or meter, and on a long pole we open the temporary Synergy account and arrange the connection. Western Power connects overhead poles and, on renovation work, is the party that moves a permanent meter off an occupied house. We cannot disconnect a permanent meter on an occupied home ourselves.

Can the site be single-phase or three-phase?

Yes. The application asks which one the site needs. It changes the work and it can change the network’s own fees, which we do not quote here.

How do renovation meter moves work?

We install the temporary pole and arrange for Western Power to attend. Western Power moves the house meter onto our pole. At the end, we return the meter to the house meter box on a dwarf pole. On a long pole, your electrician completes the reconnection.

Who looks after RCD testing?

The installation includes the protection required for that connection. This page does not set a testing timetable. Ongoing testing of construction equipment stays with the builder or the person in control of the site. Ask us what is included before work starts.

How is the pole removed and the account closed?

On a long pole, the account is in our name so we can disconnect the supply and recover the pole. On a dwarf pole with a temporary meter, we remove the meter and return it to Western Power, which closes the account, and there is no removal charge. A permanent meter stays with the property and is relocated later for a relocation fee. An end-of-run disconnection has to redirect the mains into the house at the same time. We cannot leave a disconnected meter on site.

What affects the cost?

Connection type, single-phase or three-phase, whether we supply the meter, and whether we enter a Western Power pit. Our scope and the network’s own fees are separate. We do not publish a price list, and we do not copy Western Power or Synergy fees onto this site. We confirm the scope before you proceed.

Where do you work, and how do we contact you?

Greater Perth and selected country regions. Office: 7 Browning Road, Armadale WA 6112. Phone (08) 6330 8899. Email reception@watemppower.com.au. Licence EC008678.

Need help choosing a connection for your site?

Contact us